-
Clinker Cooler 
Drive Project -
The old
system's had been designed at the end of 1980's with hard
wired controls using
Proportional Valves NG 16 for open loop control, ( see picture
)
Main
problems on the type of control was:
- the Hydraulic Control via the 4WRZ 16
combined with Inlet Pressure Compensator
was used in a closed loop control circuit,
where this Valves are for open loop;
- with the long hose lines between the
valves and the cylinder the response time
made this system to slow and weak, with
the result that the accuracy was not
very reliable;
- the best
Synchronization on the two Axis's was 2 to 3mm and with higher
demand / faster stroking speed this Synchronization Error
increased, causing often time complete Plant Shut down;
- Set up via the hard wired control cards was difficult and
fault finding took long time
- Faults in the control system was often only recognized in
the Central Control Room, when the Plant had to be shut down;
- It was not possible to keep Oil Cleanliness of the hydraulic
system as required by the Proportional Valves, the System
filters had all
By - Pass Valves, causing short life time of the Valves;
- even with the introduction in the years 1991 to 1992 of
Systems with PLC Controls, it was only possible to improve
the accuracy of this
systems to 1,5mm to 2,0mm, where this error increased at higher
speed;
- The system Pressure was not stable at stroking speed from
16spm up to 25spm, causing more miss Alignment.
With this
Problems in mind German Hydraulic & Plant Service Inc.
worked on the engineering to Modernization the CLINKER COOLER
DRIVES with the
following objectives:
Factory
Automation
Accuracy
Reliability, Safety of operation based on 24Hours 360 days
The
requirements for the new engineering:
Control
of Stroking Speed from 4 up to 25 double strokes per minute;
Control the Alignment of the Cross Head Shaft 6 to 8m lengths
with accuracy from 1mm or less over the whole range of speed,
under changing load condition;
under changing temperature conditions
Control of Position
Reliability based on 24hours operation, 360 days a year
Full communication with other PLC's with in the Factory
Signal exchange through BUS System
Longer
Life time of all used hydraulic components under the most
difficult condition in the Cement Industry;

The
Pictures here showing the new installation, where now is used
a smaller
Valve NG 10 for CLOSED LOOP control
Type: 4 WRE 10 E1-75-2X/G24K4
Where the Control Block is mounted directly
on the Cylinder, to be able to eliminate the
Flexible Hose Lines, which increases the
accuracy of the control.
In
the foreground can be seen the Stroke Transducer in a protective
Cylinder,
the Cylinder is Oil filled to lubricate the Seals.
| System
for 4.000T/day Kiln
Max Flow : 560L/min
Pressure : 120bar / 210bar
Force
on Cross Head Shaft : 50T
Speed : 4 to 25spm ( double Stroke )
Operation : 24hours
Accuracy : 0,5mm ( Synchronization )
|
| |
With the
Proportional Valves with Electrical Feedback directly mounted
on the Cylinders, this Part of the Control is now very stiff,
the accuracy and response time increased.
The
Filtration of the System was improved, the Filters now have
no By Pass Valve, the Filtration
Area was increased, to be able to have the Required Cleanliness
of the Hydraulic Fluid and at the same time to extend the
service interval!
To
reach a stable Pressure Supply at 130bar respective 210bar,
even on Higher stroking speeds above 17spm, we installed one
additional Bladder Accumulator ( 35L ) and changed the pre
Charge pressure on them to accommodate the required Flow of
maximum 560L/min, but still having one Pump as a stand by
Pump.
The
Hard of the control is for each Grate independent PLC's with
Allen Bradley Logix 5500 Controller and
Modern VT - VRPA 2-1X/ for Valves with
Electrical Feedback used for closed
Loop controls.
he
PLC has a very short scan time, the Transducer
signals can be used over
the whole range.
With
the PLC we are able to spread the Signals used so that the
setting for INPUT and OUTPUT are in same value levels.
With
this PLC the DIAGNOSTIC of Faults and the OBSERVATION of the
System Is made very easy, this makes it possible to establish
a trend, helping
The maintenance of the Grate Clinker Cooler;
For
the communication with the Plant Main Controller / Central
Control Room we installed PROFI BUS System's on each of the
Grate Clinker Coolers, with this all Indications at the CCR
are given in real time / real data.
The Pressure
Sensors on each of the Cylinder will Sense the Load Pressure
to the PLC, which in turn will adopted the System Pressure
according to the mechanical Load in the Clinker Cooler via
the Dual Pressure Compensator mounted on the each of
the Hydraulic Pumps, this allows the Pumps to work with two
fully Independent Pressure settings.
When the
mechanical Load at the Grate Controls is Low, the Pumps will
work on 130bar, in case the Load is increased, because of
Kiln Coating Brake out or other reasons, the Pumps will work
with 210bar.
The system
as shown here, was commissioned and tested, the accuracy of
Synchronization is between 0,28mm to max 0,41mm, independent
from Load or Stroking Speed.
The System is in full operation under maximum Kiln Production,
which was at the time of this installation increased by the
Customer.
to top page
|